Resource Management Act, RMA

Timeframes under the Resource Management Act

The Resource Management Act sets maximum times for processing applications and notifying relevant parties of the decision.

Time limits vary depending on whether a hearing is required. For example, a decision on a non-notified controlled activity must be made within 20 working days of receiving all the required information.

A decision on a notified discretionary activity, which attracts public submissions, must be made within 70 days. Timeframes may be extended where further information is required or at the applicant's request.

This is a brief guide only. More detailed information is available from the Council. You should also seek additional advice from a resource management or planning consultant, surveyor or solicitor.

To find out more on the Resource Management Act (RMA) visit the following website www.rma.govt.nz.




 


       