Second ETA over-bridge constructed
MEDIA RELEASE
30 November 2009
Second ETA over-bridge being constructed on Centennial Drive
In mid-December a small section of Centennial Drive will be temporarily closed to allow a 220 tonne crane to lift the concrete bridge beams into place for the new Centennial Drive bridge.
The two lane bridge will be 22 metres long and is part of the Centennial Drive Interchange which includes on and off ramps providing access to and from the ETA to Centennial Drive.
The section of Centennial Drive which will be affected is between Owen Delany Drive and west of the Laminex entrance. The road will be closed from 5.00am Monday 21 December through until 6.00pm Wednesday 23 December 2009.
There will be full access during the closure to the Taupo Native Plant Nursery and Department of Conservation driveway from the eastern side of Centennial Drive and access to the Taupo Clay Target Club and the new Taupo Dog Pound from the western side of Centennial Drive.
A detour will be in place via Broadlands Road and Tauhara Road during the closure