Lake Terrace infrastructure upgrades
Project updates
12 JULY 2024
Lake Terrace infrastructure progressing well
The new water and wastewater infrastructure along Lake Terrace is well on track, with nearly a kilometre of pipe installed so far. A further 480m of sewer main have now been welded - you can’t miss it if you drive past Taharepa Reserve - and is ready to be installed.
31 MAY 2024
New sewer main progressing well
The installation of a new sewer main along Lake Terrace is making good progress, with work now moving to the Wharewaka area. This is the second phase of the project, with work being carried out along Lake Terrace from the Wharewaka Underpass area to Richmond Avenue.
Wherever possible the team will be drilling under existing footpaths and roundabouts, but there will be some open trenching at times so please use caution around the work sites and follow the directions of the traffic management team. This phase of the work should be completed by the end of June.
8 MARCH 2024
Infrastructure upgrades blessed and under way
A formal blessing by the Reverend Peace Mitchell has marked the start of a significant upgrade to Taupō’s wastewater network. The blessing was held at Kaimanawa Reserve on Wednesday morning, with representatives from iwi, Council, and contractors in attendance.