Mangakino sewer network upgrade
Project overview
Location: | Mangakino |
Project status: | Stage two in progress |
Start date: | June 2020 |
Completion date: | November 2020
(Stage one was completed in October 2018) |
Project budget: | $2.85 million |
The Mangakino wastewater system is being upgraded with an extensive relining programme.
The relining involves inspecting the existing pipes and using robotic cutters to remove any sharp objects like roots before they are relined with an expanding polyvinyl chloride (PVC) pipe. Because the relining smooths over areas that previously would have caught items that had been flushed, it means blockages are greatly reduced. The relining also prevents water from heavy rain events seeping into the pipe system and inundating the wastewater treatment plant.
The PVC pipe has a rated life span much longer than previously used materials and the relining process is both faster than trenching and relaying pipes, as well as providing a 50 per cent cost saving.
The project is expected to be completed by November 2020, weather permitting, by which time the entire Mangakino sewer network of over 18km will have been checked and upgraded where needed.
Project updates
JUNE 22, 2020
Contractors are back on the tools in Mangakino following the move to alert level one as part of the country’s COVID-19 response.
Over the coming months, six kilometres of sewer pipes will be checked and relined to make the network more resilient, work that follows on from 6.8kms of pipes that were checked and relined in 2018.
The work is expected to be completed by November, weather permitting.
Media release June 22, 2020: Work resumes on Mangakino sewer network upgrade
Media release May 4, 2018: Wastewater upgrade underway in Mangakino