Waipapa Road slip repairs
Project overview
Work to repair several slip sites along Waipapa Road, north of Mangakino, has been completed following extensive damage caused by heavy rain in February this year.
The repairs were needed to restore the safety and long-term stability of the road which had three significant slip locations. Each slip site required excavation, drainage installation, slope rebuilding, and full road surface reinstatement.
A full road closure along Waipapa Road, from about 7km north of Mangakino to just south of Waipapa Dam, was in place 24/7 from Tuesday 7 April until the repairs were completed. Residents in the area continued to have access to their properties.
We appreciate everybody's patience and cooperation while our contractors, HEB Construction, carried out these essential works.
| Location: | Waipapa Road North of Mangakino |
|---|---|
| Project status: | Completed |
| Contractor: | HEB Construction |
| Start date: | April 2026 |
| Completion date: | May 2026 |