Wastewater buffer tanks
Project overview
We’re installing underground buffer tanks near the traffic lights on Wairakei Drive to help protect our wastewater network and local waterways.
The tanks are designed to temporarily store surges in wastewater and stormwater when the network is under pressure during heavy rain. The tanks will then release flows gradually to the wastewater treatment plant which helps to reduce the risk of wastewater overflows. As the population north of Control Gates bridge continues to grow, this project adds further resilience to our wastewater network.
Two tanks are being installed six metres below ground and will hold around 300 cubic metres of wastewater during peak flows. Once the work is complete, the tanks will be virtually invisible. While these buffer tanks will be the first to be installed in the Taupō District, they are being used successfully in Auckland, Hamilton, Wellington and other parts of New Zealand.
Our contractor MAP Projects is getting started on installing the buffer tanks in July. The project, which is being done in partnership with local hapū and marae, is expected to wrap up at the end of October.
| Location: | Nukuhau, Taupō |
|---|---|
| Project status: | In progress |
| Contractor: | MAP Projects |
| Start date: | July 2026 |
| Completion date: | October 2026 |
Why we’re doing this work
Nukuhau is growing, which means more wastewater is being generated and moving through the network. At the same time, more frequent heavier rain and severe weather events can allow stormwater to enter the wastewater system, putting extra pressure on the network - increasing the risk of wastewater overflows.
Wastewater treatment plants work best when flows are steady and predictable. Buffer tanks will give the network extra storage when flows are high, giving the treatment plant a more manageable flow. This reduces the chance of the system becoming overloaded and ultimately helps protect our precious local waterways.
What to expect during construction
- Contractors will be working on the grassy area to the north-west of the Wairakei Drive and Norman Smith Street intersection.
- Most of the work will be contained within the construction site.
- There should be minimal disruption to the wider community, with all roads and footpaths in the area remaining open at all times.
- Please take care around the worksite and follow the directions of any signage or crew working in the area.
- If you’re driving past, please keep moving safely and avoid slowing down to look at the works.
Project timeline
- July 2026: Site establishment and excavation begins.
- August to October 2026: Tank installation and associated works.
- End of October 2026: Expected completion, weather and site conditions permitting.
How you can help protect our waterways
While the buffer tanks will play a significant role in improving the resilience of our wastewater network, we all have a role to play in protecting our precious waterways. Three key things we can all do to help:
- Only flush the three Ps: Pee, poo and toilet paper. Wet wipes, even those labelled flushable, can cause blockages. Learn more about how wipes block pipes.
- Check your gully traps: Make sure stormwater from roofs, driveways or drains is not flowing into your wastewater gully trap.
- Report wastewater issues: If you notice a wastewater overflow or problem, please contact us so it can be investigated.
Stay up-to-date
We’ll share updates as the project takes shape and if there are any changes to timing, traffic impacts or other information. You can stay up-to-date by: