Centennial Drive water supply upgrade
Project overview
Work is underway to upgrade the main water pipe that supplies the Centennial Drive network, and connect it to the Taupō town water supply.
The Centennial Drive network supplies drinking water to about 70 properties in the Rakaunui Road industrial area. Extending the town supply means residents and businesses in the area will get a safe, reliable water supply that meets drinking water standards, without the need to construct a new water treatment plant.
The work will be carried out in stages, with the new water pipe being installed in the shoulder of Spa Road, Centennial Drive, Rakaunui Road and Aratiatia Road, as part of the first stage.
Once the pipe is in we will also be doing some upgrades to residential supplies in Rifle Range Road, Pihanga Street, Spa Road, Motutahae Street and Motutere Street. This stage of the project will be happening in mid-late 2027.
The project will see approximately 9km of new water pipes installed and is due to be completed in December 2027.
| Location: | Rakanui Road industrial area Taupō |
| Project status: | In progress |
| Contractor: | Nolan Drainage |
| Start date: | November 2026 |
| Completion date: | December 2027 |
Centennial Drive water supply scheme area
Project stages and timeframes
This work will be carried out in stages starting in November 2026 and is expected to be finished in December 2027. Please note timeframes are subject to change due to weather or ground conditions.
- Stage 1 - November 2026 to May 2027: new water pipe installed along Spa Road, Centennial Drive, Rakaunui Road and Aratiatia Road
- Stage 2 - April to December 2027: upgrades to residential supplies in Rifle Range Road, Pihanga Street, Spa Road, Motutahae Street and Motutere Street.
What to expect during installation
The hours of work will generally be 7.30am to 6pm Monday to Friday. In some cases, where works are required around busy intersections, nights works may be carried out to minimise disruption.
No work will occur on public holidays, over Christmas (21 December 2026 to 8 January 2027) or during the Taupō Ironman event (1-7 March 2027).
We understand that construction works are noisy and disruptive, and we will do our best to complete works as efficiently as possible. We apologise for any inconvenience caused during this time as we work on this essential piece of infrastructure.
Roads, traffic management, footpaths and access
- There will be a one-day closure during the first stage of the project for east-bound traffic heading along Spa Road (at the Tauhara Road intersection), with traffic diverted via the AC Baths. The closure and detour will be clearly signposted.
- To keep road users safe and ensure our team have a safe work site, traffic management will be in place throughout this project. This will include Stop/Go closures, shoulder and footpath closures, and some roadside parking may also be restricted near our work sites.
- Where footpaths are closed, temporary pedestrian access will be signposted with safety ramps in place. Our staff will be available during daytime working hours to assist pedestrians where required.
- Due to the nature of this work, there may be times where access to driveways is restricted due to the movement of equipment, machinery, and other materials. Our team will do their best to inform you of any potential access restrictions ahead of time to minimise disruption.
- Please follow the signage and directions from traffic management staff and speak to one of our friendly team if you need assistance.
Worksites and excavations
- Directional drilling will be used to install the new mains in most locations, however some open trenching may be used at times, if needed.
- All excavations will be backfilled, fenced off, and secured at the end of each working day.
Water supply and shutdowns
- Water supply to properties in the area will continue as normal throughout the project.
- Some localised water shutdowns will be required in the industrial area when we connect to the town network. We will contact affected property owners closer to the time with more information once details are confirmed.
Stay up-to-date
We’ll share updates as the project takes shape and if there are any changes to timing, access or other information. You can stay up-to-date by:
- Subscribing to our weekly Connect Korero e-newsletter
- Following us on Facebook and Instagram
- Downloading the Antenno app to get council notifications sent directly to your phone.
Questions
If you have any queries throughout this project, please contact us. Thanks for your patience and co-operation while work is underway.